Operating permit: Boilers, pressure vessels, and refrigeration equipment and systems

An operating permit is required to operate and maintain specific types of regulated boilers, pressure vessels, and refrigeration equipment or systems in BC. Operating permits confirm that equipment maintenance is performed or monitored by qualified individuals. This information is used by Technical Safety BC to determine maintenance and assessment needs, and provide information on safety hazards related to boiler equipment or systems.

Owners of equipment or managers of premises, where regulated equipment is located, are required to pull operating permits.

Examples of premises where regulated equipment and systems may be located are:

  • Commercial properties
  • Industrial plants
  • Mills
  • Manufacturing plants
  • Multi-unit office buildings
  • Multi-unit residential buildings with 5 or more self-contained residential units
  • Schools, hospitals, and municipal facilities

Registration of a boiler plant, which may comprise a single, larger boiler or an array of boilers, is now required. This provides Technical Safety BC with better oversight of risk and clarifies plant classification and staffing requirements for asset owners.

The time to apply for an operating permit is:

  • before you operate equipment or perform maintenance;
  • when you acquire property (existing permits become invalid when properties change ownership); and/or
  • as part of an ongoing renewal process, as long as the equipment is in service.

Apply and get an operating permit for:

An operating permit is required for the following types of equipment and systems.

  • High pressure steam boilers with a heating surface area exceeding 2 m²
  • Low pressure thermal fluid boilers with a heating surface area exceeding 3 m2
  • Low pressure steam and hot water boilers with a heating surface area exceeding 3 m²
  • Hot potable water heaters exceeding 120 kW or 400,000 BTU/hr
  • Digesters
  • Pressure vessels operating at and with relief valves set at a pressure exceeding 103 kPa
  • Refrigeration systems exceeding 25 kW prime mover nameplate capacity rating using Group A3, B2 or B3 refrigerant
  • Refrigeration systems exceeding 125 kW prime mover nameplate capacity rating using Group Al, A2 or B1 refrigerant

To apply for an operating permit

  1. A safety officer must inspect any of the equipment listed above before you can receive an operating permit. To request an inspection, submit a completed form online.
  2. Once the equipment has passed inspection, you will receive your certificate of inspection, followed by an invoice for both the inspection and your operating permit. See details on fees here. Note: Fees are not refundable.
      2018 2019 2020
    High pressure boilers, low pressure boilers, thermal fluid boilers with a heating surface:
    (a) up to and including 25 m2 $258 $263 $268
    (b) from 25.1 m2to 50 m2 $388 $396 $404
    (c) from 50.1 m2 to 100 m2 $472 $481 $491
    (d) from 100.1 m2 to 500 m2 $686 $700 $714
    (e) more than 500.1 to 1,000 m2 $1,331 $1,358 $1,385
    (f) more than 1,000.1 to 2,000 m2 $1,545 $1,576 $1,608
    Additional charge per 1,000 m2 of heating surface over 2,000 m2 rounded up to the nearest 1,000 m2 $515 $525 $536
    Hot water boilers with a heating surface:
    (a) up to and including 25 m2 $128 $131 $134
    (b) from 25.1 m2 to 50 m2 $154 $157 $160
    (c) from 50.1 m2 to 100 m2 $171 $174 $177
    (d) from 100.1 m2 to 500 m2 $258 $263 $268
    (e) from 500.1 m2 to 1,000 m2 $472 $481 $491
    (f) more than 1,000.1 m2 to 2,000 m2 $601 $613 $625
    Additional charge per 1,000 m2 of heating surface over 2,000 m2 rounded up to the nearest 1,000 m2 $214 $218 $222
    Digesters
    Shell volumetric measurement less than 280 m3 $515 $525 $536
    Shell volumetric measurement more than 580.1 m3 $823 $839 $856
    Refrigeration plants
    More than 125 kW prime mover nameplate capacity rating using Group A1, A2, or B1 refrigerant, or more than 25 kW prime mover nameplate capacity rating using Group A3, B2, or B3 refrigerant $377 $385 $393
    Table B: Regular Service (steam, air, gas, liquid service which is non-lethal, non-cyclic)
      Length
    Diameter <5M 5‐10M 10‐15M 15‐20M  20‐25M >25M
    <1M 44 72 109 146 183 217
    1‐2M 67 95 132 169 206 240
    2‐3M 86 114 151 188 225 259
    3‐4M 109 137 174 211 248 282
    4‐5M 128 156 193 230 267 301
    >5M 151 179 216 253 290 324

     

    Table C: Designated Service (non-lethal but corrosive or cyclic service)
      Length
    Diameter <5M 5‐10M 10‐15M 15‐20M  20‐25M >25M
    <1M 88 146 217 290 362 434
    1‐2M 131 189 260 333 405 477
    2‐3M 172 230 301 374 446 518
    3‐4M 214 272 343 416 488 560
    4‐5M 256 314 385 458 530 602
    >5M 300 358 429 502 574 646

     

    Table D: Special Service (lethal service)
      Length
    Diameter <5M 5‐10M 10‐15M 15‐20M  20‐25M >25M
    <1M 135 217 325 434 543 652
    1‐2M 201 283 391 500 609 718
    2‐3M 260 342 450 559 668 777
    3‐4M 327 409 517 626 735 844
    4‐5M 388 470 578 687 796 905
    >5M 453 535 643 752 861 970

     

    Table E: LPG Service - February 1, 2018
      Length
    Diameter <5M 5‐10M 10‐15M 15‐20M  20‐25M >25M
    <1M 29 43 68 87 111 133
    1‐2M 40 54 79 98 122 144
    2‐3M 57 71 96 115 139 161
    3‐4M 68 82 107 126 150 172
    4‐5M 78 92 117 136 160 182
    >5M 93 107 132 151 175 197
  3. Once the invoice has been paid, you will receive your operating permit.
  4. The permit needs to be stored alongside the equipment.

Annual renewal

Operating permits must be renewed annually. You will receive an invoice before a permit expires.

Technical Safety BC now requires the registration of a plant as a whole operating system (e.g. a single large boiler, or an array of multiple small boilers) to confirm and classify the plant's use, and assignment of certified operators.

Qualifying boiler plants in commercial, industrial, institutional, or public assembly buildings, are required to have an operating permit.

To register a plant and obtain an operating permit, see here.

Any regulated boiler, refrigeration system, and pressure vessel system in a building that contains five or more self-contained residential units, will require an operating permit.

Application Process

  1. A safety officer must inspect any of the equipment listed above before you can receive an operating permit. To request an inspection, submit a completed form online.
  2. Once the equipment has passed inspection, you will receive your certificate of inspection, followed by an invoice for both the inspection and your operating permit. See details on fees here. Note: Fees are not refundable.
  3. Once the invoice has been paid, you will receive your operating permit.
  4. The permit needs to be stored alongside the equipment.

Annual renewal

Operating permits must be renewed annually. You will receive an invoice before a permit expires.

If you are decommissioning your boiler, pressure vessel or refrigeration/HVAC system, please submit a completed Operating Permit Declaration of Status Change - All Technologies Form 1539

 